Shifting logs

Correct log depths with cable stretch and other errors by adding a segment to the top or bottom of one or multiple logs in the current synthetic. New data points added to the top or bottom of logs are extrapolated using the last available data point. If the top or bottom value is anomalous, it will be propagated and may require further editing.

GeoSyn requires that all logs have the same top and bottom, so when one log is shifted in depth, GeoSyn adds data to the top or bottom of all logs to compensate.

The time datum can also be changes using the Edit > Time Datum menu option. For details, see Related topics below.

To shift logs:

1. From the Edit menu, select Log editing ().

OR

Double-click the log

OR

Right-click the log and select Log editing.

The Log Editor dialog box opens.

2. In the toolbar beside the Log Editor, click the Shift tool ().

The Shift Curve dialog box opens.

3. In the display pane, select the logs to shift. SHIFT+CLICK or CTRL+CLICK for multiple selection.

4. Type a signed value to shift the log(s) in the Shift selected curves box then click Apply.

Related topics